SANDLER

Programme: 12 weeks

Client: Sandler Seating

Contract team project manager: Sid Smith Project Management

Designers: Spark & Trebble

Mechanical Electrical Consultants: Brinson Staniland Partnership

Main Contractor: Polyteck

Polyteck worked closely with the clients project management team, including interior designers and M&E consultants, Brinson Staniland Partnership, to deliver the project on time and within budget over a12 week period on a warehouse / office building in North London.

The fit out comprised both an industrial design, appropriate for the mass volume upholstery and production works being carried out, and a high end commercial design and showroom suitable for the office staff and potential clients.

Works included:

  • Construction of a double and single story steel framed mezzanine within the warehouse
  • Full fire protection to the new mezzanines and existing structure
  • Upgrading of incoming Electric and Gas utility supplies
  • New Air Conditioning and Ventilation Throughout.
  • New flooring and ceilings throughout.
  • New bespoke veneered doors
  • Improvement of existing W/C facilities
  • Full decorations throughout
  • Creating of roof access internally from warehouse, including fall arrest system on roof.
  • Full electrical re-wire and installation of energy efficient fittings.
  • Installation of external shutters
  • Manufacture and installation of custom joinery and finishes.